Schedule
90
2020-12-28
Pictures of work in progress,December 2020.
Completion of installation of walk-in cooler at preparation area, kitchen dumbwaiters, and kitchen hoods. The continuati...
117
2020-11-27
Pictures of work in progress,November 2020.
The installation of kitchen dumbwaiters, walk-in cooler, and kitchen equipment
134
2020-10-28
Pictures of work in progress,October 2020.
Completion of the installation of window panels, doors, and kitchen equipment
172
2020-09-28
Pictures of work in progress,September 2020.
Installation of the elevator, window panels and doors were delivered and the installation began, staff started preparing...
148
2020-08-27
Pictures of work in progress,August 2020.
Completion of elevator well and all electrical power construction
137
2020-05-28
Pictures of work in progress,May 2020.
Completion of the interior structure remodeling and reinforcement
129
2020-01-28
Pictures of work in progress,January 2020.
Beginning of the interior structure remodeling
136
2019-12-30
Pictures of work in progress,December 2019.
Beginning of the interior structure reinforcement due to the hollow old structure
127
2019-11-28
Pictures of work in progress,November 2019.
Completion of the excavation of elevator well and the concrete installation
149
2019-09-29
Pictures of work in progress,September 2019.
Re-installation of underground water pipelines